Seems like somebody forgot something.
Workers preparing Pilgrim Park Middle School for a new heating and ventilation system discovered unexpected asbestos and wiring issues that will increase costs by $120,000, but district officials expect the project to finish on budget.
...Some areas of the school had faulty or missing smoke and security censors. Another find: a "considerable portion" of communications system wiring was replaced several years ago, but never connected - the system continued to be operating off the old wiring. Workers also discovered improperly supported wiring.
So: who was the contractor?